[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101756":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101756,779,2,"多选题","某项目施工过程中，由于空中飞行物坠落给施工造成了重大损害，( )应当由承包方承担。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包方人员伤亡损失",true,{"key":16,"text":17,"correct":18},"B","发包方人员伤亡损失",false,{"key":20,"text":21,"correct":14},"C","承包方施工设备损坏的损失",{"key":23,"text":24,"correct":18},"D","运至施工场地待安装工程设备的损害",{"key":26,"text":27,"correct":18},"E","工程修复费用","AC","2020版教材P110 本题考查的是不可抗力。通用条款规定，不可抗力造成的损失由发包人和承包人分别承担:(1)永久工程，包括己运至施工场地的材料和工程设备的损害，以及因工程损害造成的第三者人员伤亡和财产损失由发包人承担;(2) 承包人设备的损坏由承包人承担;(3) 发包人和承包人各自承担其人员伤亡和其他财产损失及其相关费用;(4) 停工损失由承包人承担，但停工期间应监理人要求照管工程和清理、修复工程的金额由发包人承担;(5) 不能按期竣工的，应合理延长工期，承包人不需支付逾期竣工违约金。发包人要求赶工的，承包人应采取赶工措施，赶工费用由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]