[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101751":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101751,779,2,"多选题","施工合同履行中，承包人采购的材料经检验合格后已在施工中使用，工程师后来再次检验发现材料不符合设计要求，则( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人负责拆除",true,{"key":16,"text":17,"correct":14},"B","承包人承担拆除发生的费用",{"key":19,"text":20,"correct":21},"C","发包人承担拆除发生的费用",false,{"key":23,"text":24,"correct":14},"D","延误的工期不予顺延",{"key":26,"text":27,"correct":21},"E","已完成的工程应予计量支付","ABD","2020版教材P102-104 本题考查的是施工质量管理。重新试验和检验的结果证明该项材料、工程设备或工程的质量不符合合同要求，由此增加的费用和(或)工期延误由承包人承担 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]