[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101741":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101741,779,2,"多选题","根据《人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释（二）》，合同双方对开工日期有争议的，可以按照（ ）规定来确定。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人或者监理人发出的开工通知载明的开工日期",true,{"key":16,"text":17,"correct":14},"B","开工通知发出后，尚不具备开工条件的，以开工条件具备的时间为开工日期",{"key":19,"text":20,"correct":14},"C","因承包人原因导致开工时间推迟的，以开工通知载明的时间为开工日期",{"key":22,"text":23,"correct":24},"D","发包人或监理人未发出开工通知，亦无相关证据证明实际开工日期的，应以施工合同中载明的日期为竣工日期",false,{"key":26,"text":27,"correct":14},"E","承包人经发包人同意已经实际进场施工的，以实际进场施工时间为开工日期","ABCE","本题考查的是监理人职责。。选项D，发包人或者监理人未发出开工通知，亦无相关证据证明实际开工日期的，应当综合考虑开工报告、合同、施工许可证、竣工验收报告或者竣工验收备案表等载明的时间，并结合是否具备开工条件的事实，认定开工日期。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]