[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101733":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101733,779,2,"多选题","根据《标准施工合同》，关于市场物价浮动对同价格影响的说法错误的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工期12月以上的公司合同，不考虑市场价格变化对施工成本的影响",false,{"key":16,"text":17,"correct":14},"B","发包人和承包人共同分担市场价格变化风险",{"key":19,"text":20,"correct":21},"C","施工合同价格可采用票据法进行调整",true,{"key":23,"text":24,"correct":21},"D","调整价格的方法适用于工程量清单中所有工程款",{"key":26,"text":27,"correct":14},"E","总价支付部分不考虑物价浮动对合同价格的调整","CD","2020版教材P93-95 标准施工合同的规定：工期12月以上的公司合同，由于承包人在投标阶段不可能合理预测一年以后的市场价格变化，因此应设有调价条款，由发包人和承包人共同分担市场价格变化的风险。标准施工合同通用条款规定用公式法调价，但调整价格的方法仅适用于工程量清单中按单价支付部分的工程款，总价支付部分不考虑物价浮动对合同价格的调整。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]