[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101727":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101727,779,2,"多选题","在施工组织设计中需要经5人以上专家论证的危险性较大的分部分项工程的专项施工方案有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","深基坑工程",true,{"key":16,"text":17,"correct":14},"B","地下暗挖工程",{"key":19,"text":20,"correct":14},"C","高大模板工程",{"key":22,"text":23,"correct":24},"D","高空作业工程",false,{"key":26,"text":27,"correct":24},"E","深水作业工程","ABC","2020版教材P97-98 在施工组织设计中应针对深基坑工程、地下暗挖工程、高大模板工程、高空作业工程、深水作业工程、大爆破工程的施工编制专项施工方案。对于前3项危险性较大的分部分项工程的专项施工，还需经5人以上专家论证方案的安全性和可靠性。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]