[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101725":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101725,779,2,"多选题","承包人应按合同约定的工作内容和施工进度要求，编制施工组织设计和施工进度计划，并对所有施工作业和施工方法的( )负责。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","完备性",true,{"key":16,"text":17,"correct":14},"B","安全性",{"key":19,"text":20,"correct":14},"C","可靠性",{"key":22,"text":23,"correct":24},"D","准确性",false,{"key":26,"text":27,"correct":24},"E","及时性","ABC","2020版教材P97-98 本题考查的是承包人的义务。承包人应按合同约定的工作内容和施工进度要求，编制施工组织设计和施工进度计划，并对所有施工作业和施工方法的完备性、安全性、可靠性负责 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]