[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101723":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101723,779,2,"多选题","施工准备阶段，属于发包人应完成的工作有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","办理土地征用",true,{"key":16,"text":17,"correct":18},"B","向工程师提供工程进度计划",false,{"key":20,"text":21,"correct":18},"C","提供保证施工安全需要的围栏设施",{"key":23,"text":24,"correct":14},"D","办理现场外临时道路的通行权",{"key":26,"text":27,"correct":14},"E","组织设计单位向承包人进行图纸交底","ADE","2020版教材P96-97 发包人义务：(一)提供施工场地，发包人应及时完成施工场地的征用、移民、拆迁工作；发包人应根据合同工程的施工需要，负责办理取得出人施工场地的专用和临时道路的通行权；(二)组织设计交底；(三)约定开工时间。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]