[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101719":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101719,779,2,"多选题","根据《标准施工合同》，关于市场物价浮动对合同价格的影响，表述正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期12个月以上工程不考虑市场价格变化对施工成本的影响",false,{"key":16,"text":17,"correct":18},"B","发包人和承包人共同分担市场价格变化风险",true,{"key":20,"text":21,"correct":18},"C","施工合同价格可采用公式法进行调整",{"key":23,"text":24,"correct":18},"D","总价支付部分不考虑物价浮动对合同价格的调整",{"key":26,"text":27,"correct":14},"E","适用于工期在12个月以内的简明施工合同的通用条款没有调价条款","BCD","本题考查的是订立合同时需要明确的内容。简明施工合同规定：适用于工期在12个月以内的简明施工合同的通用条款没有调价条款，承包人在投标报价中合理考虑市场价格变化对施工成本的影响，合同履行期间不考虑市场价格变化调整合同价款。标准施工合同的规定：工期12个月以上的施工合同，由于承包人在投标阶段不可能合理预测一年以后的市场价格变化，因此应设有调价条款，由发包人和承包人共同分担市场价格变化的风险。标准施工合同",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]