[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101690":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101690,779,2,"多选题","关于建设工程勘察合同内容的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","勘察人需对发包人提供的文件资料进行核查，并对其准确性负责",false,{"key":16,"text":17,"correct":14},"B","对工程的勘察许可应由勘察人提供",{"key":19,"text":20,"correct":21},"C","勘察工作范围地下已有埋藏物的资料应由发包人提供",true,{"key":23,"text":24,"correct":21},"D","建筑总平面布置图由发包人提供",{"key":26,"text":27,"correct":14},"E","拆除地下障碍物应由承包人完成","CD","2020版教材P76-78 发包人应及时向勘察人提供下列文件资料，并对其准确性、可靠性负责，通常包括: (1)本工程的批准文件(复印件) ，以及用地(附红线范罔)、施工、勘察许可等批件(复印件)。(2) 工程勘察任务委托书、技术要求和工作范围的地形图、建筑总平面布置图。(3) 勘察工作范围已有的技术资料及工程所需的坐标与标高资料。(4) 勘察工作范围地下已有埋藏物的资料(如电力、电信电缆、各种管道、人防设施、洞室等)及具体位置分布图。(5) 其他必要相关资料。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]