[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101686,779,2,"多选题","建设工程勘察合同履行管理中，关于合同价格与支付说法正确的有（）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","勘察费用实行发包人签证制度",true,{"key":16,"text":17,"correct":14},"B","勘察合同的价款确定方式、调整方式和风险范围划分，在专用合同条款中约定",{"key":19,"text":20,"correct":14},"C","定金或预付款的额度、支付方式及抵扣方式在专用合同条款中约定",{"key":22,"text":23,"correct":24},"D","发包人应在收到定金或预付款支付申请后14天内，将定金或预付款支付给勘察人",false,{"key":26,"text":27,"correct":24},"E","发包人要求勘察人进行外出考察、试验检测、专项咨询或专家评审时，相应费用包含在合同价格之中","ABC","2020版教材P78-83 发包人要求勘察人进行外出考察、试验检测、专项咨询或专家评审时，相应费用不含在合同价格之中，由发包人另行支付。 发包人应在收到定金或预付款支付申请后28 天内，将定金或预付款支付给勘察人",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]