[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101671":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101671,779,2,"多选题","勘察人在与发包人签订合同时提交了履约保函，关于该保函的说法正确的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","有效期自合同签订之日起开始",false,{"key":16,"text":17,"correct":14},"B","至签收最后一批勘察成果文件之日后失效",{"key":19,"text":20,"correct":21},"C","担保人在收到发包人的赔偿要求后7日内支付",true,{"key":23,"text":24,"correct":14},"D","发包人和勘察人变更合同，只有征得担保人同意后，担保人继续承担担保义务",{"key":26,"text":27,"correct":21},"E","属于无条件的、不可撤销担保","CE","（1）担保有效期自发包人与勘察人签订的合同生效之日起至发包人签收最后一批勘察成果文件之日起28日后失效。 （2）担保有效期内，如果勘察人不履行合同约定的义务或其履行不符合合同的约定，担保人在收到发包人以书面形式提出的在担保金额内的赔偿要求后，在7日内无条件支付。 （3）无条件的、不可撤销担保：发包人和勘察人变更合同时，无论担保人是否收到该变更，担保人承担担保规定的义务不变。（票据无因性：票据行为与作为其发生前提的实质性原因关系相分离，从而使票据行为的效力独立存在，不再受原因关系的影响。）",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]