[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101654":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101654,779,2,"多选题","勘察人布置勘探工作时，应当充分考虑勘探方法对于（）和其他物体的影响，采用切实有效的措施进行防范控制，不得造成损坏或中断运行。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","自然环境",true,{"key":16,"text":17,"correct":14},"B","周边设施",{"key":19,"text":20,"correct":14},"C","建构筑物",{"key":22,"text":23,"correct":14},"D","地下管线",{"key":25,"text":26,"correct":27},"E","设计便捷",false,"ABCD","2020版教材P78-83 勘察人布置勘探工作时，应当充分考虑勘探方法对于自然环境、周边设施、建构筑物、地下管线、架空线和其他物体的影响，采用切实有效的措施进行防范控制，不得造成损坏或中断运行，否则由此导致的费用增加和(或)周期延误由勘察人自行承担。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]