[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101595,779,1,"单选题","实行设计总包的，按照合同约定或经招标人同意，设计单位（ ），将建筑工程非主体部分的设计进行分包。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","必须通过公开招标方式",false,{"key":16,"text":17,"correct":14},"B","必须通知邀请招标方式",{"key":19,"text":20,"correct":21},"C","可以不通过招标方式",true,{"key":23,"text":24,"correct":14},"D","只能通过协议方式","知识点:设计总包分包的规定。实行设计总包的，按照合同约定或经招标人同意，设计单位可以不通过招标的方式将建筑工程非主体部分的设计进行分包。2020版教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]