[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101587,779,1,"单选题","CM模式中，如果工程实际总费用超过保证工程最大费用（GMP）时，超过部分由（ ）承担，即管理性承包的含义。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","雇主",false,{"key":16,"text":17,"correct":18},"B","CM承包商",true,{"key":20,"text":21,"correct":14},"C","总承包商",{"key":23,"text":24,"correct":14},"D","工程师","知识点:美国AIA合同文本。当工程实际总费用超过GMP时，超过部分由CM承包商承担，体现了CM管理承包的风险性，也使业主方造价控制风险大大降低。2020版教材P165",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]