[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101586,779,1,"单选题","根据IPD合同条件，若项目实际成本超出目标成本，根据合同约定，业主可选择不再偿付任何单位的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员成本",true,{"key":16,"text":17,"correct":18},"B","材料成本",false,{"key":20,"text":21,"correct":18},"C","设备成本",{"key":23,"text":24,"correct":18},"D","分包成本","知识点:IPD合同模式。若项目实际成本超出目标成本，业主可选择不再偿付任何单位的人员成本，只支付材料、设备和分包成本。2020版教材P166。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]