[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101578,779,1,"单选题","在FIDIC设计采购施工EPC合同条件中，除非另有约定，对于不可预见的困难，承包商（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不能调整合同价款",true,{"key":16,"text":17,"correct":18},"B","可以调整合同价款",false,{"key":20,"text":21,"correct":18},"C","分不可预困难的具体情况区别对待，部分可以调整",{"key":23,"text":24,"correct":18},"D","根据不可预见困难发生的时期区别对待，部分可以调整","知识点:《设计采购施工（EPC）\u002F交钥匙合同条件》中不可预见的困难。承包商应被认为已取得了对工程可能产生影响和作用的有关风险、意外事件和其他情况的全部必要资料。合同价格对任何不可预见的困难或费用不应考虑给予调整。2020版教材P160。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]