[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101575,779,1,"单选题","根据FIDIC《施工合同条件》 ，工程师在收到索赔是报告或证明资料后（ ）天内，或在工程师可能建议并经承包商认可的其它期限内，做出回应。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14天",false,{"key":16,"text":17,"correct":14},"B","28天",{"key":19,"text":20,"correct":21},"C","42天",true,{"key":23,"text":24,"correct":14},"D","56天","知识点:《施工合同条件》索赔的程序。工程师在收到索赔报告或证明资料后42天内，或在工程师可能建议并经承包商认可的其他期限内，做出回应。2020版教材P156。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]