[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101574,779,1,"单选题","根据FIDIC《施工合同条件》，可以调整合同约定单价的条件之一是：工程量的变动直接导致该项工作每单位成本的变动超过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.01%",false,{"key":16,"text":17,"correct":18},"B","1%",true,{"key":20,"text":21,"correct":14},"C","5%",{"key":23,"text":24,"correct":14},"D","10%","本题考查《施工合同条件》中允许调整合同单价的条件。此项工作测量的工程量比工程量表或其他拫表中规定的工程量的变动超过10%。工程量的变动与费率的乘积超过了中标合同额的0.01%。工程量的变动直接导致该项工作每单位成本的变动超过1%。2020版教材P154。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]