[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101573,779,1,"单选题","根据FIDIC施工合同条件，对永久工程每项工程的计量，应以（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A图纸净值",false,{"key":16,"text":17,"correct":14},"B","双方签证确定的净值",{"key":19,"text":20,"correct":21},"C","实际完成的净值",true,{"key":23,"text":24,"correct":14},"D","考虑膨胀、收缩或浪费在内的实际完成值","知识点:《施工合同条件》典型条款分析。工程计量的方法。对永久工程每项工程应以实际完成的净值计算，不考虑膨胀、收缩或浪费。 2020版教材P154。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]