[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101570,779,1,"单选题","对于大型工程为了检验承包人的设计、设备选型和运行情况等是否满足合同约定，会在缺陷责任期内工程稳定运行一段时间后，进行竣工后试验。竣工后试验由（ ）组织，应在试验日期提前（ ）通知对方。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人，14天",false,{"key":16,"text":17,"correct":14},"B","发包人，14天",{"key":19,"text":20,"correct":14},"C","承包人或发包人，14天",{"key":22,"text":23,"correct":24},"D","承包人或发包人，21天",true,"知识点:缺陷责任期管理。竣工后试验按专用条款的约定由发包人或承包人进行。发包人应将竣工后试验的日期提前21天通知承包人。2020版教材P137。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]