[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101567,779,1,"单选题","根据《设计施工总承包合同》，总承包项目的竣工试验，承包人应提前（ ）将申请竣工试验的通知送达监理人。监理人应在（ ）内，确定竣工试验的具体时间。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","28天，28天",false,{"key":16,"text":17,"correct":14},"B","14天，7天",{"key":19,"text":20,"correct":21},"C","21天，14天",true,{"key":23,"text":24,"correct":14},"D","28天，21天","知识点:工程总承包项目竣工验收的时间。承包人应提前21天将申请竣工试验的通知送达监理人，并按照专用条款约定的份数，向监理人提交竣工记录、暂行操作和维修手册。监理人应在14天内，确定竣工试验的具体时间。2020版教材P136。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]