[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101566,779,1,"单选题","设计施工总承包合同模式下，承包人只可以索赔费用的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人提供的材料、设备不符合要求",false,{"key":16,"text":17,"correct":14},"B","发包人原因指示的暂停施工",{"key":19,"text":20,"correct":21},"C","发包人要求提前交货",true,{"key":23,"text":24,"correct":14},"D","隐蔽工程的重新检验证明质量合格","知识点:索赔管理。选项A，可以索赔工期和费用，选项BD，工期、费用和利润均可索赔。2020版教材P133。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]