[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101564,779,1,"单选题","根据《标准设计施工总承包合同》，由于异常恶劣的气侯条件带来的延误与损失，（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不能顺延工程，不能补偿费用和利润",false,{"key":16,"text":17,"correct":14},"B","可以顺延工程，但不能补偿费用和利润",{"key":19,"text":20,"correct":21},"C","可以顺延工程，可以补偿费用但不能补偿利润",true,{"key":23,"text":24,"correct":14},"D","可以顺延工程，可以补偿费用和利润","知识点:合同的索赔管理。异常恶劣的气侯条件，可以顺延工程，可以补偿费用但不能补偿利润。2020版教材P133。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]