[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101561,779,1,"单选题","设计施工总承包合同中，监理人获得发包人同意后应提前（ ）向承包人发出开始工作通知。因发包人原因造成监理人未能在合同签订之日起（ ）天内发出开始工作通知，承包人有权提出价格调整要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7天，90天",true,{"key":16,"text":17,"correct":18},"B","7天，30天",false,{"key":20,"text":21,"correct":18},"C","14天，90天",{"key":23,"text":24,"correct":18},"D","14天，30天","知识点:开始工作。监理人获得发包人同意后应提前7天向承包人发出开始工作通知；因发包人原因造成监理人未能在合同签订之日起90天内发出开始工作通知，承包人有权提出价格调整要求，或者解除合同。2020版教材P127。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]