[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101551,779,1,"单选题","以下有关监理工程师及监理工程师授权的人员的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人应在发出开始工作通知前14天将总监理工程师的任命通知承包人",false,{"key":16,"text":17,"correct":14},"B","总监理工程师更换时，应提前14天通知承包人并征得承包人的同意",{"key":19,"text":20,"correct":21},"C","总监理工程师超过2天不能履行职责的，应委派代表代行其职责，并通知承包人",true,{"key":23,"text":24,"correct":14},"D","总监理工程师可以将自己的所有权力授权给其它监理人员","知识点:工程总承包合同有关各方管理职责。选项A ，发包人任命总监理工程师没有提到时间的限制。选项B，总监理工程师更换时，应提前14天通知承包人，但并不需要征得承包人的同意。选项D，总监理工程师不应将约定应由总监理工程师作出确定的权力授权或委托给其他监理人员 。2020版教材P121。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]