[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101545":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":21,"analysis":24},1101545,779,1,"单选题","在设备采购招标中，如综合评价值相同的，将依照第一级评价因素（ ）的优先次序，根据其评价值高低进行排序。",[11,15,17,20],{"key":12,"text":13,"correct":14},"A","技术、价格、商务、服务",false,{"key":16,"text":13,"correct":14},"B",{"key":18,"text":19,"correct":14},"C","价格、技术、服务、商务",{"key":21,"text":22,"correct":23},"D","价格、技术、商务、服务",true,"知识点:设备采购招标中的综合评估法的因素。综合评价值相同的，将依照第一级评价因素价格、技术、商务、服务的优先次序，根据其评价值高低进行排序。2020版教材P74。",{"id":6,"name":26,"category":27,"favorite":28},"合同管理","建筑工程",0]