[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101544,779,1,"单选题","在材料采购招标中，合同条款中规定预付款为合同总价的15%，如果投标人提出预付款需按合同总价的20%支付，则可按招标文件规定的年利率计算出合同总价（ ）提前付款后的利息，在评标价中（ ）这笔金额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%，加上",true,{"key":16,"text":17,"correct":18},"B","5%，减去",false,{"key":20,"text":21,"correct":18},"C","20%，加上",{"key":23,"text":24,"correct":18},"D","20%，减去","知识点:材料招标中最低评标价法因素的调整。对招标人不利的要在报价上加上。投标文件对此有偏离但又属招标文件允许的，评标时将按招标文件中规定的利率计算提前支付所产生的利息，并将其计入其评标价中。2020版教材P69。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]