[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101540,779,1,"单选题","以下有关材料招标文件要求的说法，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标文件中的实质性要求和条件，不满足其中任何一项实质性要求和条件的投标将被拒绝",false,{"key":16,"text":17,"correct":14},"B","非实质性要求和条件，应规定允许偏差的最大范围、最高项数，以及对这些偏差进行调整的方法",{"key":19,"text":20,"correct":14},"C","主要材料或者供货合同的主要部分不得要求或者允许分包",{"key":22,"text":23,"correct":24},"D","招标人不得允许中标人对非主体货物进行分包",true,"知识点:材料招标文件中招标人要求的规定。招标人允许中标人对非主体货物进行分包。2020版教材P66。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]