[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101537,779,1,"单选题","CIP价（指定目的地价）中卖方承担（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","货物运至目的地的运费，不包括保险费",false,{"key":16,"text":17,"correct":18},"B","货物运至目的地的运费和保险费",true,{"key":20,"text":21,"correct":14},"C","货物运输至进口港之前的一切费用",{"key":23,"text":24,"correct":14},"D","货物在装船港装上船之前的一切费用","知识点:材料设备采购招投标报价方式。选项A，包含运费和保险费。选项C为到岸价，选项D，为离岸价。2020版教材P64。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]