[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101532,779,1,"单选题","根据《标准施工招标文件》，下列评审工作中，不属于综合评估法的初步评审阶段工作内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","形式评审",false,{"key":16,"text":17,"correct":14},"B","资格评审",{"key":19,"text":20,"correct":14},"C","响应性评审",{"key":22,"text":23,"correct":24},"D","施工方案合理性评审",true,"知识点:综合评估法。综合评估法初步评审包含形式评审标准、资格评审标准和响应性评审三个方面。2020版教材P58。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]