[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101518,779,1,"单选题","某工程招标中，投标文件的内容未完全响应招标文件，但仍属于有效投标文件的情况是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","联合体投标没有提交联合体协议书",false,{"key":16,"text":17,"correct":14},"B","投标工期长于招标文件中要求的工期",{"key":19,"text":20,"correct":14},"C","投标保函金额少于招标文件的要求",{"key":22,"text":23,"correct":24},"D","未详细说明使用专利施工的技术细节",true,"知识点:评标、决标阶段的工作。评标委员会首先通过初步评审，检查各投标书是否响应了招标文件的要求，淘汰对招标文件没有做出响应或存在重大偏差的投标书。选项D属于投标文件对招标文件反应的细微差别。2020版教材P42。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]