[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101517,779,1,"单选题","关于评标委员会组成的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人代表2人，专家6人",false,{"key":16,"text":17,"correct":18},"B","招标人代表2人，专家5人",true,{"key":20,"text":21,"correct":14},"C","招标人代表2人，专家4人",{"key":23,"text":24,"correct":14},"D","招标人代表2人，专家3人","知识点:评标、决标阶段的工作。成员人数为5人以上单数，其中招标人以外的专家不得少于成员总数的2\u002F3。2020版教材P43。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]