[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101510,779,1,"单选题","根据九部委设备采购合同的规定，由于买方原因在最后一批合同设备交货后（ ）内未能开始考核，则买卖双方应在上述期限届满后（ ）内或专用合同条款另行约定的时间内签署验收款支付函。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7日，3日",false,{"key":16,"text":17,"correct":14},"B","28日，3日",{"key":19,"text":20,"correct":14},"C","3个月，7日",{"key":22,"text":23,"correct":24},"D","6个月，7日",true,"知识点:材料采购合同履行管理。如由于买方原因在最后一批合同设备交货后6 个月内未能开始考核，则买卖双方应在上述期限届满后7 日内或专用合同条款另行约定的时间内签署验收款支付函。2020版教材P149。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]