[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101503,779,1,"单选题","根据《标准材料设备采购合同》以下合同文件中：1.投标函；2.商务和技术偏差表； 3.技术服务和质保期服务计划；4.中标设备技术性能指标的详细描述；5.分项报价表；6.供货要求。效力排序正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1-6-2-4-5-3",false,{"key":16,"text":17,"correct":14},"B","1-6-2-5-4-3",{"key":19,"text":20,"correct":21},"C","1-2-6-5-4-3",true,{"key":23,"text":24,"correct":14},"D","1-2-5-6-3-5","知识点:材料设备采购合同文件的效力。合同协议书；中标通知书；投标函；商务和技术偏差表；专用合同条款；通用合同条款；供货要求；分项报价表；中标设备技术性能指标的详细描述；技术服务和质保期服务计划；其他合同文件。2020版教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]