[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101502,779,1,"单选题","由于承包人原因未在约定的工期内竣工的，则对原约定竣工日期后继续施工的工程，在使用价格调整公式进行价格调整时，应使用的现行价格指数是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","原约定竣工日期的价格指数",false,{"key":16,"text":17,"correct":14},"B","实际竣工日期的价格指数",{"key":19,"text":20,"correct":21},"C","原约定竣工日期与实际竣工日期的两个价格指数中较低者",true,{"key":23,"text":24,"correct":14},"D","原约定竣工日期与实际竣工日期的两个价格指数中较高者","知识点:调价公式。惩罚违约者原则，承包人违约则就低原则。2020版教材P106",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]