[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101499,779,1,"单选题","根据《标准施工合同》，判定是提前竣工还是延误竣工是比较（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同内约定的工期和合同工期",false,{"key":16,"text":17,"correct":14},"B","缺陷责任期和质保期",{"key":19,"text":20,"correct":14},"C","施工期和合同内约定的工期",{"key":22,"text":23,"correct":24},"D","施工期与合同工期",true,"知识点:保修期。施工期与合同工期比较，判定是提前竣工还是延误竣工。2020版教材P99。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]