[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101497,779,1,"单选题","根据《标准施工合同》，因承包人原因逾期竣工时，承包人应支付逾期竣工违约金，最高赔偿限额为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程结算价的2%",false,{"key":16,"text":17,"correct":14},"B","签约合同价的2%",{"key":19,"text":20,"correct":14},"C","工程结算价的3%",{"key":22,"text":23,"correct":24},"D","签约合同价的3%",true,"知识点:施工进度管理。最高赔偿限额为签约合同价的3%。2020版教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]