[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101496,779,1,"单选题","在施工合同履行过程中发生紧急情况，监理人未及时下达暂停施工指示，承包人先暂停施工，并向监理人提出暂停施工的书面请求。监理人在24小时内未答复，视为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同意承包人的暂停施工请求",true,{"key":16,"text":17,"correct":18},"B","不同意承包人的暂停施工请求",false,{"key":20,"text":21,"correct":18},"C","须继续等待24小时方是规定的回复期限",{"key":23,"text":24,"correct":18},"D","必须马上复工","知识点:施工进度管理。紧急情况下的暂停施工，由于发包人原因发生暂停施工的紧急情况，且监理人未及时下达暂停施工指示，承包人可先暂停施工并及时向监理人提出暂停施工的书面请求。监理人应在接到书面请求后的24小时内予以答复，逾期未答复视为同意承包人的暂停施工请求。2020版教材P102。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]