[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101494,779,1,"单选题","“不利气候条件” 对施工的影响属于（ ）应承担的风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","保险人","知识点:施工进度管理。“异常恶劣的气候条件”属于发包人的责任；“不利气候条件” 对施工的影响则属于承包人应承担的风险。2020版教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]