[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101493,779,1,"单选题","根据《施工合同标准文本》的规定，在工程量的计量中，总价子目结算通常（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不进行现场计量，只进行图纸计量",true,{"key":16,"text":17,"correct":18},"B","进行现场计量，不进行图纸计量",false,{"key":20,"text":21,"correct":18},"C","现场计量和图纸计量必须均进行",{"key":23,"text":24,"correct":18},"D","无须进行现场计量和图纸计量","知识点:工程款支付管理。单价子目的计量，需要进行现场的计量，总价子目结算通常不进行现场计量，只进行图纸计量。2020版教材P106。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]