[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101492":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101492,779,1,"单选题","根据《标准施工合同》，竣工验收基本合格但提出了需要整修和完善要求，经监理人复查整修和完善工作达到了要求，再签发工程接收证书，这种情况下竣工日为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收申请报告之日",true,{"key":16,"text":17,"correct":18},"B","整修和完善工作完成日",false,{"key":20,"text":21,"correct":18},"C","承包人重新提交竣工验收报告的日期",{"key":23,"text":24,"correct":18},"D","工程接收证书颁发日","知识点:竣工验收管理。要区别竣工验收基本合格但提出了需要整修和完善要求这种情况，和第一次验收不合格第二次验收合格这两种情况。经监理人复查整修和完善工作达到了要求，再签发工程接收证书，竣工日仍为承包人提交竣工验收申请报告的日期。2020版教材P116。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]