[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101490,779,1,"单选题","某工程在缺陷责任期内，因施工质量问题出现重大缺陷，发包人通知承包人进行维修，承包人不能在合理时间内进行维修，发包人委托其他单位进行修复，修复费用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","使用人",{"key":23,"text":24,"correct":14},"D","以上都不正确","知识点:缺陷责任期。缺陷责任期内如果承包人不能在合理时间内修复缺陷，发包人可以自行修复或委托其他人修复，修复费用由缺陷原因的责任方承担。本题是施工质量问题，所以由承包人承担。2020版教材P117。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]