[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101489,779,1,"单选题","（ ）以后承包人就失去索赔的权利。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程颁发接收证书",false,{"key":16,"text":17,"correct":14},"B","竣工结算",{"key":19,"text":20,"correct":14},"C","颁发缺陷责任终止证书",{"key":22,"text":23,"correct":24},"D","颁发结清证书",true,"知识点:缺陷责任期管理。提出索赔的期限至发包人接受最终结清证书时止，即合同终止后承包人就失去索赔的权利。2020版教材P118。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]