[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101487,779,1,"单选题","一般情况下由（ ）负责提供试运行所需的人员、器材和必要的条件，并承担全部试运行费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","设备供应商",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","监理人","知识点:竣工验收管理。一般情况承包人应负责提供试运行所需的人员、器材和必要的条件，并承担全部试运行费用。2020版教材P115。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]