[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101486":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101486,779,1,"单选题","当事人对建设工程实际竣工日期有争议，承包人已经提交竣工验收报告，发包人拖延验收的，则实际竣工日为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收合格之日",false,{"key":16,"text":17,"correct":18},"B","承包人提交竣工验收报告之日",true,{"key":20,"text":21,"correct":14},"C","实际竣工之日",{"key":23,"text":24,"correct":14},"D","转移占有之日","知识点:实际竣工日。2020版教材P115。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]