[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101483,779,1,"单选题","如果索赔事件的影响持续存在，承包商应在该项索赔事件（ ），提出最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发生后的28天内",false,{"key":16,"text":17,"correct":14},"B","全部消除后",{"key":19,"text":20,"correct":14},"C","影响结束后的14天内",{"key":22,"text":23,"correct":24},"D","影响结束后的28天内",true,"知识点:索赔管理。如果索赔事件的影响持续存在，承包人应按合理时间间隔，定期陆续报出每一个时间段内的索赔证据资料和索赔要求，在该项索赔事件的影响结束后28天内，承包人向监理人递交最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。2020版教材P111。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]