[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101482,779,1,"单选题","某工程项目由于异常不利的气侯条件，导致施工单位工期拖延且产生费用损失，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期可以顺延，但费用不予补偿",true,{"key":16,"text":17,"correct":18},"B","工期可以顺延，可以补偿费用，不能补偿利润",false,{"key":20,"text":21,"correct":18},"C","工期可以顺延，费用和补偿都可以补偿",{"key":23,"text":24,"correct":18},"D","工期、费用、利润均不能补偿","知识点:索赔的规定。异常恶劣的气候条件，可索赔工期，不能索赔费用和利润；不利的气候条件，由施工单位自己承担，不能索赔；不利的特质条件，可以索赔工期和费用，不能索赔利润。2020版教材P111。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]