[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101474,779,1,"单选题","根据《标准施工合同》，发包人提供的材料和工程设备由承包人会同监理人验收后，由承包人负责接收，由（ ）承担施工现场内的二次搬运费。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","材料供应商","知识点:施工质量管理。发包人提拱的材料和工程设备验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。2020版教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]