[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101472,779,1,"单选题","监理工程师已签字验收某隐蔽工程，覆盖后监理又怀疑该工程的质量，要求剥露重新检验，检验发现由于混凝土养护不当导致该部分工程质量确实不合格，则重检验的费用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","材料采购方","知识点:隐蔽工程的重新检验的规定。责任主要看再次检验质量是否合格。2020版教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]