[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101471,779,1,"单选题","根据《施工合同标准文本》的规定，施工工期在12个月以上的工程，由于市场价格浮动对合同价格的影响，此风险应由（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人承担",false,{"key":16,"text":17,"correct":14},"B","承包人承担",{"key":19,"text":20,"correct":21},"C","由发包人和承包人分担",true,{"key":23,"text":24,"correct":14},"D","发包人和承包人均不承担","知识点:工程款支付管理。施工工期12个月以内的简明施工合同通用条款没有调价条款，风险由承包人承担。施工工期12个月以上的工程，应考虑市场价格浮动对合同价格的影响，新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com 由发包人和承包人分担市场价格变化的风险。2020版教材P94。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]